Seminar: We all know that Works must be progressed Regularly and Diligently – or do they?

Does Leander v Mulalley affect ‘Regularly and Diligently’?

What are the Costs of Missing Programme Dates?

What does ‘your’ contract say you have to do?

Blake Newport is delighted to invite you to an evening seminar looking at what the implications of the recent Leander v Mulalley case will have on the transfer of obligations from contractors to sub-contractors.

The seminar will look at the much used and relied on phrase ‘shall regularly and diligently proceed…’ and the belief by contractors and sub-contractors alike that this requirement exists irrespective of the contract.

By reference to Leander v Mulalley we will discuss whether the term to work regularly and diligently is implied even if there is no express provision within an Agreement to do so. We will also consider details of the case and the views expressed in published texts and case law to establish exactly what a Party is required to do when there is no express provision in an Agreement stating the programme or methodology of how and when the works are to be carried out, and how the works should integrated between the contractor and sub-contractors.

As well as providing you with a view on the commercial implications of construction contracts the seminar will enable you to network with other like-minded individuals. Places are strictly limited so if you would like to attend please register as soon as possible using the form below.

We hope you will be able to join us.

Sign-up for the seminar here.

Collecting Life Long Learning?
This seminar is RICS relevant for 1hr.

Dates & Locations

17 May 2012
Browns, Covent Garden, London

24 May 2012
Charles Halle Room, Bridgewater Hall, Manchester

14 June 2012
Lumley Room, Durham County Cricket Ground, Riverside, Chester-le-Street

Blake Newport Proud to be Sponsors of CIOB NE Branch Annual Dinner 2012

Blake Newport is proud to be one of the sponsors of the CIOB North East Branch Annual Dinner on 23 March 2012.

This year’s event will take place at the Gosforth Park Marriott (near Newcastle) with Charley Boorman as speaker.

Blake Newport has taken a table at this event for the last five years and has been one of the sponsors for the last two – it is a great night for entertaining clients and networking within the North East.

Further information on the event can be found here.

HealthCheck

Margins are tight; can you afford the risk of losing them?

As we all know construction and engineering projects are complex and busy environments where, sometimes, the operation of the contract and commercial discipline can get overlooked. A Blake Newport Project HealthCheck reviews the key indicators of risk within a project and identifies which need addressing so that they can be resolved rather than project margins having to absorb them.

Blake Newport has over 30 years proven experience in both bespoke and standard forms of contracts and how to operate them. Our expertise is unrivalled in analysing and recovering additional returns to maximise our clients’ revenues or minimising the risk on existing projects.

Our tried and tested approach adopts a three phase approach:

Phase 1 – On site Commercial Audit
Phase 2 – Report and face-to-face presentation to our client
Phase 3 – Development and implementation of recommendations.

Phase 1

This is the key phase in that it identifies the nature and extent of the commercial issues or opportunities existing within the contract and on the project. A Blake Newport consultant will review key documentation including programmes for the project, using a HealthCheck form similar to this one. The time period required for this review will be 1 – 3 days depending on the size of the project.

The foundation of this phase will be the review of payment accounts, contracts, programmes, correspondence, etc.

Phase 2
Phase 2 will be conducted from Blake Newport’s office. The information gained will be analysed and written up by the consultant who conducted the HealthCheck. The report will include:

  • Brief overview of the scope of the contract
  • Synopsis of the status of the contract at the report cut off date
  • Overview of the commercial and programme status of the contract contrasted against the position as contemplated by the contract
  • Schedule of key risks identified through the process
  • Recommended next steps.

At the end of Phase 2, Blake Newport will present face-to-face the findings and analysis of the HealthCheck to the relevant Director or Manager.

Phase 3
The third Phase is optional and is not part of the fixed fee. This phase involves the preparation of a strategy and, if required, implementation of the strategy to reduce the identified risks and realise opportunities to improve the existing financial or programme position. The use of a third party, such as Blake Newport to present, discuss, negotiate and agree difficult issues with client’s, sub-contractors or suppliers provides objectivity that can often break the deadlock of commercial issues surrounding matters that may have existed for some time. The deployment of Blake Newport can also introduce a degree of distance from the detailed and often fraught resolution of contentious matters helping to preserve relationships, often built up over a number of years.

Contact us about our HealthCheck and see what we can do for you.

Construction Law Update: Concurrent Delay and Loss & Expense

Blake Newport and DWF are delighted to invite you to an evening seminar looking at Concurrent Delay and Loss & Expense on construction contracts.

Over the last 11 years confusion has reigned over seemingly contradicting decisions. Does the recent case of Adyard Abu Dhabi v SD Marine Services [2011] provide clarity as to the English Courts’ interpretation of concurrency in delay analysis?

The method of valuing loss and expense claims causes significant problems on projects. Blake Newport will discuss best practice in the valuation of loss and expense claims; providing simple and unambiguous advice to assist in developing greater
understanding.

As well as providing you with a view on construction contracts from both a legal and commercial perspective the seminar will enable you to network with other like-minded
individuals. Places are strictly limited so if you would like to attend please
register as soon as possible by clicking HERE.

We hope you will be able to join us.

Collecting CPD points?
This seminar is RICS (1 point) accredited.

Dates & Locations:
Tuesday 22 November – DWF, Leeds
Wednesday 23 November – DWF, Manchester
Thursday 24 November – DWF, Liverpool

Programme:

17.00 – Registration
17.25 – Welcome and Introduction
17.30 – Concurrent Delay – Clarity at Last? Paul Barge, Partner, DWF
 Loss & Expense – Best Practice Approach to Valution Greg Brownlee, Managing Director, Blake Newport
18.50 – Questions
19.00 – Drinks & Canapés

What SME contractors need to know

Delays, disputes and time extensions are all part of the construction sector vocabulary, but recent judgments have brought ‘concurrency’ to the fore.

Concurrent delay in a construction contract is where two or more events delay the progress of works, setting the completion date back from what was originally agreed in the contract. The contractor is the cause of one of the delays and the client is the cause of the other. The question this raises is whether the contractor is entitled to an extension of time and money and if so, by how much?

Author, John Delaney

There were a number of historical cases that looked at how to ascertain extensions of time, dependant on whether the delays took place at the same time or, alternatively, if the contractor was first responsible for causing the delay.

However, in a case in Scotland heard in 2010 – City Inn v Shepherd Construction – it was unclear which party was to blame. As a result, the “apportionment approach” was created. This is where responsibility for the delay and its consequences is divided “fair and reasonably” between the two parties.

A contract dispute between De Beers v Atos Origin has re-awakened the debate and delivered a new line of authority on what is now believed to be the position of the English courts. Here, the Court found both parties were responsible for delays and so the judge simply applied the general rule in construction and engineering cases. This is: “If there is a concurrent delay to completion caused by matters for which both employer and contractor are responsible, the contractor is entitled to an extension of time but cannot recover in respect of the loss caused by the delay.”

The judge ignored the decision in the City Inn case, relying instead on the “prevention principle”, which applies to all contracts. This stipulates that if the client prevents completion of the works beyond the contractual completion date, he/she cannot claim relief for a delay he/she has caused. This implies the delay suffered by the contractor at the hands of the client must entitle the contractor to an extension of time, irrespective of any concurrent delay.

Buyers should take note that the De Beers judgment has again changed thinking under English law and it is clear you cannot rely solely on past case law to show you when or to what extent an extension of time will be awarded. The contract and particular circumstances of the events causing the delay will require careful analysis when parties are considering extension of time claims.

Our advice to buyers is to undertake careful contract management and consider how
concurrency is addressed in your contracts for extension-of-time purposes. Ensure you are clear just how events and delays will be considered and the specifics of your particular circumstances.

This article was published in Supply Management.

Blake Newport take 11th in the Construction Industry Dragon Boat Challenge

Last month Blake Newport’s London team (plus six clients) competed in the Construction Industry Dragon Boat Challenge in North London.

After an unbalanced first race (a near capsizing seemed to slow the team down!), Blake’s Blades won its last two races. With a final aggregated time of 84.91 seconds; Blake’s Blades came a decent 11th (out of 40 boats) only just missing out on the semi final.


Other than trying to beat the other teams competing along with us, the event was organised to raise money for CRASH – by the close of the event the charity had raised over £12,000.

Conditions Precedent to Recovery of Loss and Expense Claims

According to the tax and advisory organisation KPMG, the strain of the past few years has left the construction industry increasingly confrontational in a bid to counteract narrowing margins. Companies are pricing to break-even in order to survive as well as employing contractual defences to win back margins through ADR, including adjudication. Rob Dalton, Associate Director at commercial and contract management consultancy Blake Newport explains why condition precedent clauses are catching some contractors out and why they shouldn’t rely on common case law to save them…

Condition Precedent Clauses
There are a number of provisions within construction and engineering contracts that contractors should heed. One such provision that is threatening to impact on contractors across these sectors is the growing use of condition precedent clauses.

When applied to construction and engineering contracts, condition precedent clauses are usually provisions that require notification of a claim (delay of works or rise in cost) within a specified amount of time.

For instance, clause 61.3 of NEC3 relates to the contractor’s obligation to notify compensation events and states;

“if the Contractor does not notify a Compensation Event within 8 weeks of becoming aware of the event he is not entitled to a change in the Price, the Completion Date or a Key Date unless the Project Manager should have notified the event to the contractor but did not”.

Accordingly, failure to issue the required notice is likely to result in contractors losing the right to both extension of time and additional money.

Although included in NEC3, and the FIDIC form of contract, condition precedent clauses have not generally been a feature of other standard form construction and engineering contracts. It is however becoming more common to amend these standard forms to introduce such provisions.

Enforceable or not enforceable?
In the Bremer v Vanden[1] case the House of Lords stated that for a notice issued by an employer to be considered a condition precedent, a specific time for delivery of the notice should be expressed. It should be accompanied by a clear indication of the impact of failing to issue the notice and clearly state that rights would be lost in the event that notice is not given.

In short, contractors must provide notices to their client as soon as any possible delays or additional costs become apparent; these notices must be accompanied with any relevant information that will help the employer to assess the contractor’s request.

But contractors beware!

Although they may be required to provide notice of delays or additional costs, they will not be entitled to direct loss and/or expense where their own negligence contributed or was directly responsible for it.

In another example, the case of City Inn v Shepherd Construction[2], Shepherd argued that the condition precedent clause imposed a penalty upon them, because an extension of time that they should have been entitled to had not been granted simply because they had failed to give notice and not because of any fault of the actual works. The court rejected Shepherd’s argument saying that it was always in the contractor’s power to avoid the liability, by taking the necessary steps as outlined in the contract.

So what can be done and can common law defeat a Condition Precedent?
When a contractor’s claim is rejected on the grounds that it has failed to serve notices, the contractor will often argue that the employer’s position is contrary to the ‘prevention principle’. Essentially, this means that if the client has prevented the contractor from delivering the project to the specified date, then the contractor cannot be blamed for not fulfilling their contract, as found in the case of Multiplex Construction v Honeywell Control Systems[3].

In Multiplex Construction v Honeywell Control Systems the court noted that

“one consequence of the prevention principle is that the employer cannot hold the contractor to a specified completion date if the employer has by act or omission prevented the contractor from completing by that date. Instead time becomes at large and the obligation to complete by this specified date is replaced by an implied obligation to complete within a reasonable time”.

But whilst the ‘prevention principle’ may in some cases offer some defence to condition precedents it certainly cannot be relied on. In cases such as Gaymark Investments v Walter Construction[4] and WW Gear Construction v McGee Group[5], the court has rejected the contractor’s ‘prevention principle’ defence. This was on the basis that it was always in the power of the contractor to notify the employer and protect its interests by giving the relevant notices of delay.

It is clear then that contractors must take notice of properly drafted condition precedent clauses and undertake careful commercial and contract management in order to ensure they do not fall foul of these provisions. In times like these, careful contract management will help you to not only claim for money or time owed to you but also ensure client-contractor relationships are maintained, better margins achieved and hopefully the opportunity of future projects secured.

For the full technical document and explanation of the court cases mentioned in the above summary please go to wwww.blakenewport.co.uk/downloads 


[1] Bremer v Handelgelsellschaft mbH v Vanden Avenne Izegem P.V.B.A [1978] 2 LLR 109

[2] City Inn v Shepherd Construction (2003) CILL 2009

[3] Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) [2007] EWHC 447 (TCC)

[4] Gaymark Investments Pty Ltd v Walter Construction Group [1999]

[5] WW Gear Construction Ltd v McGee Group Ltd [2010] EWHC 1460